Building Permit Requirements in Marikina, Metro Manila

(2025 Updated)

Verified

Last verified: December 3, 2024

Quick Summary

Estimated Fees

Contact City Engineering Office for current fee schedule

Processing Time

1-2 weeks including clearances

Plan Sets Required

5 sets

Documentary Requirements

Check off items as you prepare them:

  • Notarized Unified Form for Building Permit & Fire Safety Evaluation Clearance Form
  • Photocopies of PTR/PRC ID of Engineers/Architect who signed and sealed plans and forms
  • Mayor's Permit or Business Permit (in Marikina City) of the contractor/Engineer or Architect in-charge
  • Certified True Copy of Transfer Certificate of Title (TCT) from Registry of Deeds, J.P. Rizal St., Concepcion 1
  • Photocopies of Tax Declaration of Real Property (Land & Building) from Assessor's Office
  • Photocopies of Tax Receipt of Real Property for current year (Amilyar)
  • Application form for Locational Clearance from City Planning Office
  • Barangay Clearance
  • Fire Safety Evaluation Clearance (FSEC)

Required Clearances

Barangay Clearance

Fee: ₱100-500 depending on barangay
Processing: 1-3 days
  • Valid ID of applicant/owner
  • Proof of ownership (TCT or Tax Declaration)
  • Cedula

Locational Clearance

Fee: Contact City Planning Office for current fees
Processing: 3-5 working days

Where: 2nd Floor, Marikina City Hall

  • Application form from City Planning Office
  • Barangay Clearance
  • TCT or Tax Declaration copy
  • Site development plan

Fire Safety Evaluation Clearance (FSEC)

Fee: ₱1,000-5,000 depending on project size
Processing: 3-5 working days
  • Building plans with fire safety features
  • Electrical layout
  • Fire safety checklist

Tips

  • Department Head/OIC: Engr. Kennedy Sueno
  • Contact: 948-1201/02 and 948-1206
  • Location: 2nd Floor, Public Service Center Building, 5th St., Cor. Aquilina Extn., Sto. Niño
  • Fast processing: 3-5 days if requirements are complete and compliant with NBC
  • Registry of Deeds: J.P. Rizal St., Concepcion 1, Marikina City
  • Assessor's Office: Ground Floor, Marikina City Hall
  • City Planning Office: 2nd Floor, Marikina City Hall
  • Downloadable forms at marikina.gov.ph/download-forms

Common Mistakes

  • Missing PTR/PRC ID photocopies of professionals
  • Contractor without valid Marikina business permit
  • Not getting Locational Clearance first

Frequently Asked Questions

How do I contact the City Engineering Office in Marikina?

Call 948-1201/02 or 948-1206. The office is at 2nd Floor, Public Service Center Building, 5th St., Cor. Aquilina Extn., Sto. Niño, Marikina City. Department Head: Engr. Kennedy Sueno.

How long does building permit processing take in Marikina?

Marikina has one of the fastest processing times in Metro Manila - typically 3-5 days if requirements are complete and compliant with the National Building Code.

Where can I download building permit forms for Marikina?

Forms are available at marikina.gov.ph/download-forms including Unified Building Permit Form and requirements checklist.

Download Checklist

Get a printable PDF checklist for your building permit application

Email required for download

Contact Information

Where:
2nd Floor, Public Service Center Building, 5th St., Cor. Aquilina Extn., Sto. Niño, Marikina City
Hours:
Monday-Friday, 8:00 AM - 5:00 PM

Need Help?

Find contractors in Marikina who can handle permit processing

Find Contractors